Gainesville Mine Reclamation

Gainesville, GA

CLIENT: Hanson Aggregates

MARKET:
CAPABILITY:
  • 8 acres of steep slope clearing and grubbing
  • Design / build reclamation project
  • 255,000 CY of excavation
  • 1 acre waterfowl habit constructed
  • .5 acre waterfowl retriever training pond constructed
  • 30 acres of permanent grassing
  • 550 LF of stream restoration
  • 10,000,000 gallons of dewatering
  • 1,800 tons of rip rap lined channels
  • 2,400 LF of diversion channels

PROJECTS BY MARKET